Most of PSE’s engineers experienced cover all phases of the container handling equipment and motor vessel profession, from concept, to scheduling, tendering, contracting, expediting, designing, fabrication, assembling and erection, commissioning test run and maintenance. Their knowledge is multi-disciplinary, this means by multi-disciplinary, they are able to approach a problem not just from narrow prospective of their specialty, but also from different angles of various discipline.
No. | WORK ASSIGNMENT | CRANE TYPE | PROJECT NAME AND OWNER | DATE OF COMPLETION |
---|---|---|---|---|
1 | 2 | 3 | 4 | 5 |
1 | Annual Inspection | Mobile Crane & Accessories | Inspection Lifting Equipment and Accessories of Medium Range Anti-Aircraft Defence System supply by Kongsberg - Norway for the Airforce of Indonesia | October 2020 |
2 | Bidding Process | RTG & HMC | Consultant Service on Preparation of Technical Specifications and bidding for Procurement 5 (five) units Rubber Tyred Gantry (RTG) and 1 (one) unit Harbour Mobile Crane (HMC) for Terminal Berlian, PT BJTI - Surabaya | June 2020 |
3 | Bidding Process | QCC | Consultant Service on Preparation of Technical Specifications and bidding for Procurement 2 (two) units Quay Container Crane Type Super Post Panamax, PT Jakarta International Container Terminal | April 2020 |
4 | Project Management | RTG | Supervision of Procurement 16 (sixteen) units E-RTG for Makassar New Port, PT Pelabuhan Indonesia IV (Persero) | December 2019 |
5 | Project Management | RTG | Supervision of Procurement 4 (four) units E-RTG for Kendari New Port, PT Pelabuhan Indonesia IV (Persero) | December 2019 |
6 | Project Management | RTG | Supervision of Procurement 3 (three) units RTG for Terminal Petikemas Bitung, PT Pelabuhan Indonesia IV (Persero) | December 2019 |
7 | Technical Assessment | QCC | Crane Technical condition and remaining life cycle assessment on 7 (seven) units QCC in Surabaya Container Terminal, PT Terminal Petikemas Surabaya | November 2019 |
8 | Bidding Process | RTG | Consultant Service on Preparation of Technical Specifications and bidding for Procurement 4 (four) units Rubber Tyred Gantry Crane for Bitung Container Terminal and Ternate Port, PT Pelabuhan Indonesia IV (Persero) | September 2019 |
9 | Design Review | RTG | Consultant Service for Design Reviewing on Procurement 4 (four) units of New Rubber Tyred Gantry (RTG) for Bitung Container Terminal and Ternate Port, PT Pelabuhan Indonesia IV (Persero) | September 2019 |
10 | Design Review | QCC | Consultant Service for Design Review on Procurement of 3 (three) units Quay Container Crane Panamax For Branch Ports (Kendari New Port, Bitung Container Terminal and Port of Ternate), PT Pelabuhan Indonesia IV (Persero) | September 2019 |
11 | Design Review | QCC | Consultant Service for Design Review on Procurement 2 (two) units Quay Container Crane Post Panamax for Makassar New Port, PT Pelabuhan Indonesia IV (Persero) | June 2019 |
12 | Design Review | RTG | Consultant Service for Design Review on Procurement 28 (twenty eight) units RTG Crane, PT Pelabuhan Indonesia IV (Persero) | February 2019 |
13 | Project Management | RTG | Supervision on Procurement New Rubber Tyred Gantry (RTG), PT Pelabuhan Indonesia IV (Persero) | December 2018 |
14 | Project Management | Fixed Pedestal Level Luffing Crane | Supervision on Procurement of 4 (Four) units Fixed Pedestal Level Luffing Crane for Gorontalo Branch Port and Manokwari Port, PT Pelabuhan Indonesia IV (Persero). (JO. PSE-WCS) | December 2018 |
15 | Bidding Consultancy and Design Review | RTG | Bidding Consultancy Services on Design Concept Review for Procurement of 5 (five) untis RTG at Belawan International Container Crane (BICT), PT Pelabuhan Indonesia I (Persero) | November 2018 |
16 | Project Management | HMC | Supervision on Procurement 5 (five) units HMC for Cabang Tanjung Perak, PT Pelabuhan Indoensia III (Persero) | October 2018 |
17 | Bidding and Design Review | JIB Crane | Consultant Service on Bidding proces and Design Review for 4 (four) units Jib Crane type DLLC at Dermaga 7.1 – 7.2, PT Krakatau Bandar Samudera - Cilegon | October 2018 |
18 | Bidding Consultancy | QCC, RTG & HMC | Consultant Service on Preparation of Technical Specifications and bidding for Procurement of Container Handling Equipment at the Port of Kijing, PT Pelabuhan Indonesia II (Persero) | October 2018 |
19 | Bidding Consultancy | A-RTG, QCC | Consultant Service on Preparation of Technical Specifications and bidding for Procurement of 12 (twelve) units Automatic RTG and 4 (four) units STS for Terminal Petikemas Belawan Fase II, PT Prima Terminal Petikemas | July 2018 |
20 | Bidding Consultancy | HMC | Consultant Service on Preparation of Technical Specifications and bidding for Procurement of 2 (two) units Harbour Mobile Crane (HMC) at PT Prima Indonesia Logistik | July 2018 |
21 | Project Management | HMC | Consultant Service on Preparation of Technical Specifications, bidding process and supervision on Procurement 8 (eight) units New HMC (Harbor Mobile Crane) for PT Berlian Jasa Terminal Indonesia - Surabaya | June 2018 |
22 | Design Review | QCC | Consultancy Service of Detail Design Review on Procurement 2 (two) units QCC for Belawan Container Terminal, PT Pelabuhan Indonesia I (Persero) | May 2018 |
23 | Design Review | RTG | Consultancy Service of Detail Design Review on Procurement 4 (four) units RTG for Terminal Petikemas Domestik Belawan (TPKDB), PT Pelabuhan Indonesia I (Persero) | May 2018 |
24 | Project Management | Fixed Pedestal Level Luffing Crane | Supervision on Procurement and Supervision 2 (two) units Fixed Crane for Merauke Port, PT. Pelabuhan Indonesia IV (Persero) | March 2018 |
25 | Project Management | QCC | Supervision on Procurement and Supervision 2 (two) Units New QCC for Bitung Container Terminal, PT Pelabuhan Indonesia IV (Persero). JO. PSE-WCS | January 2018 |
26 | Bidding Consultancy | QCC & RTG | Consultant Service on Preparation of Technical Specifications and bidding for Procurement 2 (two) units QCC for the Belawan Container Terminal and Procurement 4 (four) Units Rubber Tyred (RTG) Crane for TPKDB, PT. Pelabuhan Indoensia I (Persero) | December 2017 |
27 | Bidding Consultancy | QCC | Consultant Service on Preparation of Technical Specifications and bidding for Procurement of Container Handling 1 (one) unit QCC of PT Pelabuhan Indonesia II (Persero) - Cabang Panjang | December 2017 |
28 | Project Management | RTG | Supervision on Procurement 5 (five) units New RTG for PT. Pelabuhan Indonesia IV (Persero). JO. PSE-WCS | December 2017 |
29 | Project Management | RTG | Supervision on Procurement 4 (four) units RTG Smart Engine for Berlian Terminal, PT Berlian Jasa Terminal Indonesia - Surabaya | April 2017 |
30 | Condition Survey | QCC | Consultant Service of Survey on Accident and Repair Cost Estimation QCC due to Accident at Terminal Petikemas Bitung, PT Pelabuhan Indonesia IV (Persero) | November 2016 |
31 | Crane Assessment | QCC | Consultant Services for Technical Condition Assessment of 2 (two) units QCC at Kariangau Container Terminal, PT Kaltim Kariangau Terminal | August 2016 |
32 | Condition Survey and Project Management | RTG | Technical condition survey and Supervision of refurbishment on 2 (two) units RTG at Kariangau Container Terminal, PT Kaltim Kariangau Terminal | August 2016 |
33 | Project Management | RTG | Supervision on Procurement 3 (three) units RTG Noell Crane for Terminal Petikemas Makassar, PT Pelabuhan Indonesia IV (Persero) | August 2016 |
34 | Bidding Consultancy | A-RTG, QCC | Consultant Service on Preparation of Technical Specifications and bidding for Procurement 8 (eight) units Automatic RTG and 3 (three) units QCC for Terminal Multipurpose Kuala Tanjung, PT Prima Multi Terminal | June 2016 |
35 | Project Management | RTG | Supervision on Procurement 3 (three) units New RTG for Kariangau Container Terminal, PT Kaltim Kariangau Terminal. JO. PSE-WCS | June 2015 |
36 | Project Management | RTG | Supervision on Procurement 2 (two) Units RTG for Kariangau Container Terminal, PT Kaltim Kariangau Terminal | February 2015 |
37 | Project Management | HMC | Supervision on Procurement 2 (two) units HMC for Port of Makassar, PT. Pelabuhan Indonesia IV (Persero) | September 2014 |
38 | Condition Survey and Supervision | RTG | Consultant Services on Crane Condition Survey of 4 (four) units New RTG at Kariangau Container Terminal, PT Kaltim Kariangau Terminal | April 2014 |